Monday, March
30th, 2008
‘Green’ anode
the key to first aluminium target
AN IMPRESSIVE string of key successes
in Sohar Aluminium’s Carbon Department during
March has ensured that the company’s target
date of mid-June 2008 for its first hot metal production
is eminently achievable.
On 26 March, the department produced
its first ‘good green anode’ –
an integral component of aluminium smelting and
the first step in on-going metal production.
“From the production of
the first anode, less than a week of process tuning
and equipment adjustments were necessary to produce
the quality of ‘good green’ anode that
will suit our requirements,” said General
Manager - Operations, Michel Huot.
“This success is the result
of a tremendous team work between Bechtel, Solios
Carbon and Sohar Aluminium Company, supported by
our APT experts.”
Three days later, on 29 March,
another milestone was achieved when the smelter’s
new Anode Baking Furnace was successfully started,
along with the Solios Fume Treatment Centre and
the Innovatherm’s Firing System.
“To get to this point, there
was a lot of planning, engineering, construction,
commissioning, port support, supply chain and pre-operation
team involvement. Bechtel, Solios, Innovatherm,
NKM and Sohar Aluminium worked together to reach
this milestone,” said Mr Huot.
Anodes are specific to individual
smelters and are formed using a mix of petroleum
coke and liquid pitch. The mixture is heated to
160 degrees Celcius until it forms a paste, then
it is cooled and pressed into a mould to form an
anode block.
The ‘green’ anodes
are then transferred by conveyor to the anode baking
furnace, where they are baked at temperatures of
up to 1,150°C in a pre-heating, firing and cooling
cycle which takes 18 to 20 days.
“With the start-up of the
baking furnace we are on course to produce the first
good baked anode, from green anode produced by SA,
by the second half of May, which supports first
hot metal on the scheduled date of mid June,”
Mr Huot said.
The Sohar Aluminium smelter
is in the process of being handed over by the company’s
EPCM contractor, Bechtel. To date, the smelter construction
is around 85 per cent complete and commissioning
in most areas is well underway.